Airport Projects

St. George Replacement Airport Projects

  • Geotechnical Investigation Report, which included 64 borings and 15 test pits, laboratory testing, and earthwork recommendations.
  • Mass grading and Storm Drain for Grading and Drainage Package
  • Construct Finish Grading Project, including grading for the Terminal and ARFF Building Pads, Apron, remaining VSR, FBO, GA, and Runway Safety Areas.
  • Construct Airport Landside Culinary Waterline

St. George Municipal Airport Projects

  • Rehabilitated Runway 16/34 by rotomilling 3 inches of pavement, laying a new 3 inch surface course, adjusting runway lighting to meet safety standards, and re-grading safety area
  • Constructed three new taxilanes on the west side of the airport
  • Constructed terminal apron, northwest, northeast, and east mid-field aprons
  • Constructed 3,800 foot parallel taxiway “B”
  • Rehabilitated the MIRL and MITL on taxiways “A” & “B” and runway
  • Rehabilitated Runway 16/34 requiring crack sealing and pavement overlays, including crumb rubber hot plant mix, latex rubber friction courses

Ogden-Hinckley Airport Project

  • Reconstructed Runway 03/21, the primary ILS Runway, using in-place pulverization, excavation, incorporating frost protection, and installing runway shoulder drainage.
  • Reconstructed Runway 16/34 utilizing in-place pulverization, soil stabilization, re-grading, and a bituminous surface course
  • Constructed the runway safety area and ILS critical area grading for a new ILS installation Designed and reconstructed Runway 16/34 utilizing in-place pulverization, soil stabilization, re-grading, and a bituminous surface course
  • Overlaid Runway 16/34 with an open-graded porous friction course
  • Reconstructed the airport terminal apron using Portland cement concrete to meet higher aircraft weight requirements.
  • Constructed two new taxilanes in southeast hangar area
  • Rehabilitated five tie-down and holding aprons
  • Constructed new parking apron for Kemp facility

Brigham City Municipal Airport Projects

  • Constructed 1,400 foot Runway 16 extension
  • Rehabilitated Runway 16-34
  • Constructed a new full length parallel taxiway and connectors
  • Constructed runway and taxiway subsurface and side drainage system
  • Constructed runway and taxiway storm drain system with pump stations
  • Constructed a new taxilane for the north and south aprons
  • Constructed new aircraft apron
  • Widened runway 16/34 from 75' to 100' using soil stabilization techniques
  • Constructed new category B-II runway safety area using soil stabilization techniques

Monticello Municipal Airport Project

  • Currently constructing Runway 16/34, Taxiways, Apron, and Access Road Grading, consisting of approximately 500,000 cubic yards of P-152 Embankment
  • Construct 1,500 lineal feet of D-701 Storm Drain Pipe
  • Construct 19,500 lineal feet of D-705 Pipe Underdrain along edges of future runway and taxiways

Grand Canyon West Airport Projects

  • Constructed new Water and Sanitary Sewer pipelines
  • Currently constructing a temporary airport terminal, fuel tanks, electrical generators, and extensive site concrete work, which includes a large bus turnaround
  • Grading and Drainage for 5,000 foot Runway 17/53, which includes approximately 166,500 cubic yards of P-152 Excavation and 51,425 square yards of P-209 Crushed Aggregate Base Course

Kayenta Airport

  • Reconstruct 7,100 foot Runway 5/23 with associated taxiways and apron
  • Relocate Airport Entrance Road
  • Construct intersection of relocated Airport Entrance Road and U.S. Highway 160, including acceleration and deceleration lanes meeting ADOT standards

Lincoln County Airport

  • Apron Reconstruction and Expansion
  • Construct Runway 17 Bypass Taxiways
  • Reconstruct Runway 17/35
  • Relocate Access Road

Cedar City Regional Airport

  • Construct North Hangar Area
  • Construct Taxi lanes 1 and 2, including P-152 Embankment, P-208 Crushed Aggregate Base Course, and P-401 Asphalt Pavement
  • Install utility corridor to North Hangar Area

Nephi Municipal Airport Project

  • Constructed new 6,300 foot runway and associated taxiways
  • Expanded and reconstructed tie-down apron

Cal Black Memorial Airport Projects

  • Constructed new 5,700 foot runway and associated taxiways
  • Constructed new 200 x 700 foot tie-down apron
  • Constructed new full length parallel taxiway and two connector taxiways between Runway 01/19 and parallel taxiway
  • Constructed Fuel Farm facility with two, 10,000 gallon tanks, pumping systems, and concrete spill retention basins

Kanab Municipal Airport Project

  • Reconstructed and lengthened the runway to 6,200 feet
  • Constructed runway overlay with porous friction course.

Panguitch Municipal Airport Project

  • Relocated, lengthened, and constructed new 5700 foot category B-II runway
  • Constructed additional tie-down apron
  • Rehabilitation of the runway using rotomilling, and a new bituminous surface course

Other Airport Improvement Projects

  • Page Arizona Municipal Airport Projects - A.I.P. 3-04-0025-10, 3-04-0025-15&16
  • Parawon Municipal Airport Projects - A.I.P. 3-49-0050-05, 3-49-0050-07
  • Colorado City, Arizona Airport Project - A.I.P. 3-04-0076-07
  • Escalante Municipal Airport Project - A.I.P. 3-49-0007-02
  • Beaver Municipal Airport Project - A.I.P. 3-49-0001-05
  • Green River Municipal Airport Project - A.I.P. 3-49-0010-07
  • Richfield Municipal Airport Project - A.I.P. 3-49-0028-05